How do I change the start date of my project?

RE: Microsoft Project

Hi Tracey

Thank you for your question. You can set the start date of your project by going to the Project menu and choosing Project Information. To change the start date of an existing project (before progress has been recorded) switch on the Analysis toolbar by choosing View > Toolbars > Analysis then click on the Adjust dates button. Enter the new date and click OK.

I hope this helps do let us know if you have any further questions.

Kind regards,
Andrew

Tue 10 Mar 2009: Automatically marked as resolved.

MS Project tip:

Using the Quick Access Toolbar in Project 2010

The Quick Access Toolbar is included in virtually every Office product, including Project 2010 as well as Outlook 2010, Word 2010, Excel 2010, and PowerPoint 2010.

You will find the Quick Access Toolbar in the top-left side of the window. To begin, click the Customize button (it's the little black arrow at the end of the toolbar).

Simply click the commands you want to include.

Virtually any command can be added to the Quick Access Toolbar. Click the More Commands option and a new window will open from where you can browse the commands including those not on the ribbon.

View all MS Project hints and tips

Connect with us:

0207 987 3777

Call for assistance

Request Callback

We will call you back

Server loaded in 0.11 secs.