Tracey has attended:
Project Introduction course
Microsoft Project
How do I change the start date of my project?
RE: Microsoft Project
Hi Tracey
Thank you for your question. You can set the start date of your project by going to the Project menu and choosing Project Information. To change the start date of an existing project (before progress has been recorded) switch on the Analysis toolbar by choosing View > Toolbars > Analysis then click on the Adjust dates button. Enter the new date and click OK.
I hope this helps do let us know if you have any further questions.
Kind regards,
Andrew