Public Schedule Face-to-Face & Online Instructor-Led Training - View dates & book

milestones

ResolvedVersion 2003

Debbie has attended:
Project Introduction course

Milestones

How do I create a milestone

RE: Milestones

Debbie
Sorry for the late reply. Welcome to the forum.

In the duration column, set the duration for 0 days.

regards

Best Team

Tue 3 Mar 2009: Automatically marked as resolved.

MS Project tip:

Link tasks using predecessor column - project

a. First, note ID number of the task you want to link to (predecessor). Then, in the predecessor column of the task you want to link to (successor), type the predecessor task's ID number.
b. The link will be a Finish to Start (the default type).
c. Or you can add in a code for a different relationship type
i. SS = Start to Start
ii. FF = Finish to Finish
iii. SF = Start to Finish
d. You don't have to type the task ID numbers in any specific order, but you must separate multiple tasks with commas.

View all MS Project hints and tips

Connect with us:

0207 987 3777

Call for assistance

Request Callback

We will call you back

Server loaded in 0.09 secs.