effort driven scheduling

Forum home » Delegate support and help forum » Microsoft Project Training and help » Effort driven scheduling

Effort driven scheduling

resolvedResolved · Low Priority · Version 2007

Paul has attended:
Project Introduction course

Effort driven scheduling

How would I know when to use effort driven scheduling? HOw would I know what default to set on my copy of project.

RE: Effort driven scheduling

Hi Paul

Thanks for your question. The best way of working out whether to use effort driven scheduling or not is to consider whether or not most of the activities you are planning change duration if you add or remove resources from them.

By default Effort Driven Scheduling is on for all your tasks. To switch this off for new tasks go to Tools > Options > Schedule and remove the tick from New tasks are effort driven

Click on OK to apply this change to new tasks in your current project or click on Set as Default to apply this change to all new projects created with your installation of Project

I hope this helps - let us know if you have any further questions.

Kind regards,
Andrew

Thu 19 Feb 2009: Automatically marked as resolved.


 

MS Project tip:

Giving Someone a Gantt Chart Snapshot

To pass on a picture of a Gantt chart segment, choose the appropriate view, select the rows to be included, then click on the camera icon and select For Screen. The graphics image can be pasted into another document. (See Paste icon forn Project 2010)

View all MS Project hints and tips


Server loaded in 0.08 secs.