project training - How do I baseline a project?

resolvedResolved · Low Priority · Version Standard

Michael has attended:
Project Intro Intermediate course

How do I baseline a project?

Once I have created a plan how do I baseline it to measure progress throughout the life of the project?

Thanks.

RE: How do I baseline a project?

Hi Michael

From the Tools menu go to Tracking then choose save baseline. Project can then show you your original plan and your current progress simultaneously in the Tracking Gantt view.

Hope this helps - thanks for your question. Let us know if you need any further information.

Kind regards,

Andrew


 

MS Project tip:

Using the Quick Access Toolbar in Project 2010

The Quick Access Toolbar is included in virtually every Office product, including Project 2010 as well as Outlook 2010, Word 2010, Excel 2010, and PowerPoint 2010.

You will find the Quick Access Toolbar in the top-left side of the window. To begin, click the Customize button (it's the little black arrow at the end of the toolbar).

Simply click the commands you want to include.

Virtually any command can be added to the Quick Access Toolbar. Click the More Commands option and a new window will open from where you can browse the commands including those not on the ribbon.

View all MS Project hints and tips


Server loaded in 0.1 secs.