RE: lag time
Hi Susanne,
Thank you for your question.
If you go to Gantt chart view amd split the window via the Window menu. Select the task you want to add the lag time to and add a positive amount of days, minutes etc. in the Lag column on the right hand window of the bottom pane.
I hope this answers your question.
Regards
Simon