Lag time

how do i add lag time to a task

RE: lag time

Hi Susanne,

Thank you for your question.

If you go to Gantt chart view amd split the window via the Window menu. Select the task you want to add the lag time to and add a positive amount of days, minutes etc. in the Lag column on the right hand window of the bottom pane.

I hope this answers your question.

Regards

Simon

Mon 29 Dec 2008: Automatically marked as resolved.

MS Project tip:

Email a Task

When you need to communicate important information to your project staff use Microsoft Project 2003 to send them a note using outlook or an e-mail system.

1.In a task sheet, select the task or tasks which you want to send a project note.

2.On the File menu, point to Send To, and then select Mail Recipient (as Schedule Note).

3.Under Address message to, select the recipients of your note.