How do you change the resources for more than one task at the same time? (I've tried selecting them all together, and clickingon the task info resource tab, but only the first task was updated)

RE: Task info

Hi Sarah

As an alternative try this - split the screen (Windows > Split) then click on the task in question. In the lower part of the screen any associated resources will be displayed. Make your edits and when you are ready click OK. Project will commit the changes in one go.

I hope this helps - let us know if you have any further questions.

Kind regards,
Andrew

Mon 29 Dec 2008: Automatically marked as resolved.

MS Project tip:

Enter a Date

You can enter today's date (or tomorrow's date) in a date field, by simply typing in the word 'today'or 'tomorrow' and Project will insert the date for you.

View all MS Project hints and tips

Connect with us:

0207 987 3777

Call for assistance

Request Callback

We will call you back

Server loaded in 0.1 secs.