capacity

ResolvedVersion 2003

Maria has attended:
Project Intermediate course

Capacity

In MS Project are you able to view at what % of capacity your team is working at?

RE: Capacity

Hi Maria

One way to see this is by first splitting the screen (Window > Split) then clicking in the lower half of the screen (to make it active) and finally swtiching on the resource graph by going to View > Resource graph


Hope this helps - do let us know if you have any further questions.

Kind regards,
Andrew

Wed 3 Dec 2008: Automatically marked as resolved.

MS Project tip:

Autofit column width – Project (all versions)

At the top of the columns where each column name is located (Task Name, Duration, etc.), hover over the vertical column line which you want to move.

A short bold vertical line will appear, with horizontal arrows pointing left and right.

Left click and hold this icon and it will permit you to grab the column line, allowing you to move it left or right to your desired location.

View all MS Project hints and tips

Connect with us:

0207 987 3777

Call for assistance

Request Callback

We will call you back

Server loaded in 0.09 secs.