ResolvedVersion 2007

Joanne has attended:
Project Intro Intermediate course

Views

Can you create custom views?

RE: Views

Hi Joanne,

Thank you for your question.

If you want to create your own custom view, go to View, More Views. Select the New option and choose whether you want a Single or Combination view. Then select the relevant fields and/or Groups you want to appear in your view and click Apply.

I hope this answers your question.

Regards

Simon

MS Project tip:

Email a Task

When you need to communicate important information to your project staff use Microsoft Project 2003 to send them a note using outlook or an e-mail system.

1.In a task sheet, select the task or tasks which you want to send a project note.

2.On the File menu, point to Send To, and then select Mail Recipient (as Schedule Note).

3.Under Address message to, select the recipients of your note.