Public Schedule Face-to-Face & Online Instructor-Led Training - View dates & book

resources

ResolvedVersion 2007

Beth has attended:
Project Introduction course

Resources

Is it possible to show all the work someone has been assigned across multiple projects?

RE: Resources

Hi Beth

Thanks for your question. Yes it is possible. To do this first create a project file that just contains your resource information. This is now your resource pool. Keep the resource pool and open your project file that needs resources. From the Tools menu choose resource sharing > share resources and choose the option to use resources from the resource pool. Repeat this process with the rest of your projects.

To see a combined overview of resource assignment across all of your plans take a look at the resource usage view in your resource pool

I hope this helps - do let us know if you have any further questions.

Kind regards,
Andrew

MS Project tip:

Entering Days

To type in a day of the week, or its three letter abbreviation, in a Date field type "Monday" or "Mon", and Project will show the date for the next Monday after the current date.

View all MS Project hints and tips