Forum home » Delegate support and help forum » Microsoft Project Training and help » Exporting data from Project

Exporting data from Project

ResolvedVersion 2007

Kate has attended:
Project Intro Intermediate course

Exporting data from Project

What are the most popular ways of getting Gantt charts out of Project into a format that is user-friendly (ie for clients who don't use projects). Is Excel the solution most people use?

RE: Exporting data from Project

Hi Kate

Thanks for your question.

Probably the most straightforward way of getting your Gantt chart out to a non Project user is to go to Edit > Copy Picture then paste the results into a Word document or perhaps PowerPoint.

The export is a picture rather than the underlying data.

I hope this helps - let us know if you have any further questions.

Kind regards,
Andrew

MS Project tip:

Entering Days

To type in a day of the week, or its three letter abbreviation, in a Date field type "Monday" or "Mon", and Project will show the date for the next Monday after the current date.

View all MS Project hints and tips

Connect with us:

0207 987 3777

Call for assistance

Request Callback

We will call you back

Server loaded in 0.1 secs.