RE: resources
Hi Leon
Thanks for your question.
There are several places resources can be added into Project. A good place to start would be the resource sheet itself (View > Resource sheet) as this allows you to include additional information such as cost rates, group information and maximum units.
I hope this helps - do let us know if you have any further questions.
Kind regards,