How do you creat non uniformed work in a task? so that during 1 task 2 people are needed on eone day while 4 people are needed the next.
RE: Non Uniformed Work in Tasks
Hi Jessica
Thanks for your question. You can use one of the Usage views to precisely contour work availability. From the view menu choose Task Usage. This view presents your tasks and groups who has been assigned to them. On the right side of the screen you can modify the assignments for each day to reflect how work will be carried out.
I hope this is helpful - let us know if you have any further questions.
Kind regards,
Andrew