RE: multiple projects

Hi Katrina

Thanks for your question. You can insert a second project into your plan by going to the insert menu and choosing Insert Project.

The upper limit is driven by the specification of your machine.

Hope this is helpful, let us know if you have any further questions.

Kind regards,

Andrew

MS Project tip:

Inserting Task Durations Quickly

When entering durations for your tasks simply use the single letters - m for min, h for hr, d for day, w for week, but mon for month. If default is set for days, you need only type the number, for example 3 for 3days, or 0.5 for half a day.

View all MS Project hints and tips

Connect with us:

0207 987 3777

Call for assistance

Request Callback

We will call you back

Server loaded in 0.16 secs.