Variance

Even though i have not started any progress updation, when i switch to the variance, (from the 0 cell), the value of the variance isa showling for some tasks. what might be the reason. I havnt saved the baseline yet.

thanks
raj

RE: Variance

Hi Raj

The Variance column is automatically populated when you assign resources to rasks. When you save the baseline, it will reset the variance column to zero.

When you attend the Project course this will be covered.

Alan Burbridge
Best STL

MS Project tip:

Autofit column width – Project (all versions)

At the top of the columns where each column name is located (Task Name, Duration, etc.), hover over the vertical column line which you want to move.

A short bold vertical line will appear, with horizontal arrows pointing left and right.

Left click and hold this icon and it will permit you to grab the column line, allowing you to move it left or right to your desired location.

View all MS Project hints and tips

Connect with us:

0207 987 3777

Call for assistance

Request Callback

We will call you back

Server loaded in 0.13 secs.