Public Schedule Face-to-Face & Online Instructor-Led Training - View dates & book

resourcing

ResolvedVersion 2007

Pauline has attended:
Project Management - Framework & Processes course

Resourcing

where can I find how to create resourcing pool

RE: resourcing

Hi Pauline

You could attend our Project Advanced course!

A resource pool is a seperate Project which contains only Resource information. Each project then needs to be told to Share Resources from the Resource Pool - see the Tools menu for this option.

It is not as simple as this - you really should attend the course.

Good luck.

Alan Burbridge

MS Project tip:

Typing Links Between Tasks

In the Entry table, use the Precessors column to type in links. Type the previous task's ID to link. To change the link, add FS (Finish-Start), FF (Finish-Finish), and so on, and + duration to add a Lag, or - duration for a Lead time. Example: for task 5, 4FS+1w ... task 4 preceeds task 5, finish to start, with a week lag between.

View all MS Project hints and tips

Connect with us:

0207 987 3777

Call for assistance

Request Callback

We will call you back