How do I format the calander to class all days as work days (7 days a week)

RE: Calander

Hi David

You can do this quickly by going to Tools > Change Working Time. At the bottom of the calendar click on the Work Weeks tab. Choose the row entry called Default and click on details. Use this control to set the weekends to work days, keying in the specific hours for those days in line with the rest of the week and click OK. Before you leave change working time you might also want to click on Options and at the bottom of the screen change the hours per week from 40 (5 days) to 56 (7 days)

I hope this helps - let us know if you have any further questions.

Kind regards,
Andrew

MS Project tip:

Project Community

in the help menu type "Tips" then select "Ask the Project community" this takes you into microsofts site where you can ask questions to lots of knowledgeable people.They make up an online group of experienced Project users who answer questions and provide solutions and tips.

View all MS Project hints and tips

Connect with us:

0207 987 3777

Call for assistance

Request Callback

We will call you back

Server loaded in 0.11 secs.