Recurring Tasks
Hi there
Can you please let me know how you
assign recurring tasks in projects for example :
if i want to show weekly or monthly progress meetings as milestones on my programme
Regards
Thank you kindly.
s khan
RE: Recurring Tasks
Hi Samir
Thank you for your question
If you click on the Insert menu and select recurring tasks.
You can then use the wizard and specify
The task Name
The duration (set zero for milestones)
The recurrance pattern
The start and end dates for the first and last occurence, (if required)
Hope this is useful
If you require further advice, please get back to me
Regards
Stephen