Is it possible to apply conditional formatting specified by the user to the Gantt Chart i.e. if project is off track by a certain % can I apply certain colors?
RE: Conditional formatting
Hi Katrin
It is possible to do this. For sophisticated results you would need to customise fields and formats and possibly filters. We cover these topics in our Advanced training. However without these features you can use built in features such as format > text styles to highlight tasks that meet (built in) criteria.
I hope this is helpful - do let us know if you have any other questions.
Kind regards,
Andrew