please confirm /advise in respect of the creation of float and slack and milestones/constraints

RE: microsoft project

Hi Mark

Float is created where two tasks are linked (e.g. finish to start) and the successor is constrained beyond the finish of its predecessor. A partial constraint type is Start no earlier than SNET (reached via double clicking on the successor name then choosing the advanced tab). The successor could be a task or a milestone (0 duration).

I hope this helps. Do let us know if you have any further questions - kind regards, Andrew

MS Project tip:

Entering Days

To type in a day of the week, or its three letter abbreviation, in a Date field type "Monday" or "Mon", and Project will show the date for the next Monday after the current date.

View all MS Project hints and tips

Connect with us:

0207 987 3777

Call for assistance

Request Callback

We will call you back

Server loaded in 0.12 secs.