Forum home » Delegate support and help forum » Microsoft Project Training and help » Copying Task in Gantt Chart

Copying Task in Gantt Chart

ResolvedVersion 2007

Martin has attended:
Project Intermediate course

Copying Task in Gantt Chart

Hi,

when I copy and paste a task in Gantt Chart view, the colour of the bar doesn't copy over - it defaults to blue.

Is there any way I can copy the formatting over?

Many Thanks in Advance

Martin

RE: Copying Task in Gantt Chart

Hi Martin

I've checked and unfortunately Project will only copy/paste the formatting of the bars in the same project. If you copy and then paste to a new project the formatting reverts back to the default (generally blue) colour.

Thanks

Andrew

MS Project tip:

Compare Work and Duration

Duration is the timescale within which a task is done; Work is the specific time element used. For example, 3 days work in a duration of 2 weeks. To compare, add the Work field into the Entry table by right clicking a column heading to Add Field.

View all MS Project hints and tips

Connect with us:

0207 987 3777

Call for assistance

Request Callback

We will call you back

Server loaded in 0.11 secs.