MS project

What is the easiest way to print only the tasks?

RE: MS project

Hi Martyn

You can achieve this by going to View > more views... and choosing Task Sheet from the list. This is a view of the Project without the Gantt area. When you have finished you can go back to the normal Gantt view by repeating the process i.e. View > Gantt Chart

Hope this helps - let me know if you have any questions.

Kind regards,

Andrew

MS Project tip:

Show or hide toolbar ScreenTips

On the Tools menu, go to Customize, and then select Toolbars.
Click the Options tab.
put a tick or remove the tick from the Show ScreenTips on toolbars check box.

View all MS Project hints and tips