RE: Project

Hi John

Thanks for your question - you can block select the tasks you are interested in and from the Format menu choose Bar. This lets you set the colours of the bars for the selected tasks.

Hope this was helpful let us know if you have any other questions.

Kind regards,

Andrew

MS Project tip:

Avoid Accidental Constraints

The initial default table is the Entry table. Enter a task name and duration, but do not enter start or finish dates. Form the plan using links, predecessors. Typing dates introduces constraints. To remove these constraints, double click on a task, and on the Advanced page of Task Information set the constraint back to As Soon As Possible (all other options are there too.)

View all MS Project hints and tips

Connect with us:

0207 987 3777

Call for assistance

Request Callback

We will call you back

Server loaded in 0.16 secs.