Can you import dates from an outlook calender?

RE: MS Project

Hi Marietta,

Thank you for your question.

In Project there is no direct way of doing this. However Project has the option to import Microsoft Outlook tasks.

In Calendar view, go to View and then show the Task Pad.

So what you could do is to drag your appointments to the task pad showing on the right hand side of your calendar view and save them as a task.

Then in Project, you can use the Tools Import Outlook Tasks and then bring them in that way.

I hope this answers your question.

Regards

Simon

RE: MS Project

Simon

If you were our trainer then you very kindly went through that, not to worry i think the task thing will be useful but total importability would have been great in terms of review dates etc.

Thanks, the training was really good,

M

RE: MS Project

Hi Marietta,

Thank you for your reply.

No problem.

Regards

Simon

MS Project tip:

Create own ribbon tab - Project 2010

a. In Project click on the File tab
b. Select Options from left hand side
c. Choose the Customize Ribbon section
d. Click the New Tab button (below the list of tabs on the right hand side of the dialog box)
e. Select the New Tab (Custom) and enter a name, by clicking the Rename button (below the list of tabs on the right hand side of the dialog box)
f. Select the New Group (Custom) and enter a name, by clicking the Rename button (below the list of tabs on the right hand side of the dialog box)
g. Add commands to your tab and group by locating them on the list on the right hand side (remembering that you can change the list using the drop down box at the top of the list of commands) and clicking the Add button between the two panes to add them to your tab and group
h. You can rearrange the commands in your group, the groups on any tab or the tabs, using the up and down arrow buttons beside the list of tabs.
i. Click OK to apply your changes