I need to add more resources doing different related task working towards a common goal

RE: resources

Hi Ian

Thanks for your question. You can add more resources to a task by splitting the screen (window > split), choosing the task in question then in the lower left corner of the screen choosing your resources. Be careful though about adjusting tasks that already have resources. Project may adjust your task's duration. Check whether effort driven scheduling is enabled as well as the current task type - the controls are in the centre of the screen just below the split bar.

If you have any further questions please don't hesitate to let us know.

Kind regards,

Andrew

MS Project tip:

Gantt Charts

Gantt Charts was first Invented by Henry Gantt (1861-1919) while planning the construction of U.S. Navy ships during WWI.hence the name Gantt Charts