How do I change my task dates?
RE: Microsoft Project
Hi John
Thanks for your question - you can double click on a task and go to the advanced tab. From here you can set a task constraint (such as start no earlier than) to position your task on the Gantt chart.
Hope this is helpful - do let us know if you have any other questions.
Kind regards,
Andrew