Public Schedule Face-to-Face & Online Instructor-Led Training - View dates & book

start date

ResolvedVersion 2003

Simona has attended:
Project Intro Intermediate course
Project Advanced course

Start date

I would like to have 3 start dates for my task. When I enter another column "Start1" and choose the date the task isn't grafically displayed, it still has only one start date. How to create another start date for the same task?

RE: start date

Hi Simona

Can you tell us a little more about what you are looking to achieve?

Although you have stored a value in Start1 Project won't show you both start and start1 values simultaneously.

The PERT analysis *might* help visualise three different versions of your project though.

On the View menu, go to Toolbars> PERT Analysis.

You could click PERT Entry Sheet on the PERT toolbar and put in three durations for optimistic, expected, and pessimistic.

If you click the calculate button (4th from right) project will then populate three views of your Project. You can access these from the first three buttons on the PERT toolbar.

Alternatively you could get Project to draw bars to represent different start dates and finishes (perhaps drawing 3 lines per task) by customising the Bar Styles (Format > Bar Styles) and creating bar types for each of the different start / finish dates you are working with.

Let us know more about what you are looking to acheive and we will try and help you further.

Kind regards,

Andrew



On the PERT toolbar, starting at the far left, are three buttons that cusomise the table to show optimistic, expected, and pessimistic task information. You will see that the optimistic table has Opt Start (which is in fact Start1), The Expected view stores Exp Start in Start3 and the pessimistic value in Start3




To view the optimistic, expected, and pessimistic durations, on the PERT Analysis toolbar, click Optimistic Gantt , Expected Gantt , or Pessimistic Gantt .
To view the end dates of the three resulting schedules, on the Tools menu, click Options.
Click the View tab, and then select the Show project summary task box.

MS Project tip:

Change default view – Project 2010

a. In Project, click on the File tab
b. Select General from left hand side (this should be the screen displayed by default)
c. Set the Default view dropdown box to your chosen option
d. Click OK to apply your changes

View all MS Project hints and tips

Connect with us:

0207 987 3777

Call for assistance

Request Callback

We will call you back

Server loaded in 0.1 secs.