Public Schedule Face-to-Face & Online Instructor-Led Training - View dates & book

ms project

ResolvedVersion 2003

Jo has attended:
Project Intro Intermediate course

MS Project

If I need to set up a new project with a non optional deadline of getting a water station into operation so it can serve the local area, would that be classed as the sucessor and would it be a finish to start project(ie back to front)?

RE: MS Project

Hi Jo

Thanks for your question - good example too. The thing that would help you decide is the question: "Which of the two tasks is driving or positioning the other? Once you've chosen the predecessor (or driving task) you can then decide if it's the start or finish that's doing the driving. Finally you can assess if it's affecting the start or finish of the successor. With all that in place you may indeed end up with a task in the future being the predecessor to an earlier task with a Start Finish relationship.

Hope this helps, do let us know if you have any other questions. Kind regards,

Andrew

MS Project tip:

Show or hide toolbar ScreenTips

On the Tools menu, go to Customize, and then select Toolbars.
Click the Options tab.
put a tick or remove the tick from the Show ScreenTips on toolbars check box.

View all MS Project hints and tips

Connect with us:

0207 987 3777

Call for assistance

Request Callback

We will call you back

Server loaded in 0.15 secs.