Public Schedule Face-to-Face & Online Instructor-Led Training - View dates & book

microsoft project

ResolvedVersion 2003

Graham has attended:
Excel Advanced course

Microsoft project

how can you move non working tome to the front o a bar?

RE: microsoft project

Hi Graham

Thank you for your question

If you click on format-timescale and in the resulting dialog box, click the non working time tab. You can then choose the option to draw non working time in front of the task bars

You can also use this view to have any bank holidays defined in your project default calendar appear as non working time. To accomplish this click on the calendar combo box and select your project default calendar.

Regards

Stephen

MS Project tip:

Keep constraining dates to a minimum

As far as possible avoid fixing the dates of your tasks. For example try to steer of clear dragging task bars in the Gantt chart to move them on the timeline or entering dates directly into the Start / Finish fields.

Date constraints such as these limit Microsoft Project's ability to automatically adjust your project whenever you add, remove or modify the duration of your tasks. Instead use the logic in your task dependencies that link your tasks to enable Project to calculate the start and finish dates for you.

View all MS Project hints and tips

Connect with us:

0207 987 3777

Call for assistance

Request Callback

We will call you back

Server loaded in 0.1 secs.