Common resources

Can you have both common resources and non shared resources.

RE: Common resources

Add the pool resources first; then add the non-shared resources to the resource sheet.

MS Project tip:

Compare Work and Duration

Duration is the timescale within which a task is done; Work is the specific time element used. For example, 3 days work in a duration of 2 weeks. To compare, add the Work field into the Entry table by right clicking a column heading to Add Field.