Could I just be refreshed on the way to set up a main task with the sub tasks underneath all numbered i.e. 1.1 1.2 1.3 etc
RE: Sub sets
Hi Steve
Thank you for your question
First list the tasks with the outline task at the top and the sub tasks below it. Then select the sub tasks (not the outline task) and click on Indent. (This is the button on the top tool bar with the icon of a green arrow pointing to the right). This will create the subtasks, and the main task will be a summary of them.
To activate the numbering, Click on Tools-Options_view and choose the option button