Link tasks project plan
How do you link tasks with other tasks on a different project plan?
RE: link tasks project plan
Teqwen
From from the predecessor task link from of the plan you wish to from, type in the full path name, project name and predecessor.
ie C:\officemove\officegeneral.mpt\fs5
hope this helps
david