ms project training - Calendar

resolvedResolved · Low Priority · Version Standard

Ruth has attended:
Project Intro Intermediate course

Calendar

How do I add Bank Holidays to my calendar?

RE: Calendar

Ruth

Go to tools, select change working time, select the calendar you wish to add bank holidays to, select NON-Working Time, click OK

hope this helps

david


 

MS Project tip:

Use Autofill in MS Project

a. Complete 1st entry
b. Select cell with entry to be copied
c. Click & drag autofill handle over the lines to also contain the same information. (the autofill handle is the little black square in the bottom right hand corner of the heavy lack outline on the selected cell)