microsoft project consulting - Microsoft Project

resolvedResolved · Low Priority · Version Standard

Craig has attended:
Project Intro Intermediate course

Microsoft Project

assigning resources to tasks and tracking costs related to those resources

RE: Microsoft Project

Hi Craig

Each resource can have a cost so that when it is assigned to a task Project will calculate the cumulative cost both for the task and for the resource.

There are several ways to assign resources. A very robust and stable way to do this is to split the screen: in the Gantt view, choose window > split. Then click on the task you wish to assign resources to.

Down in the lower left half of the newly split screen you will find you can choose your resources for this task. Finally click on OK to assign them.

I hope this helps - do let us know if we can be of further assistance.

Kind regards,

Andrew


 

MS Project tip:

Format individual bars on your GANTT chart

To draw attention to a bar on your Gantt chart simply double click it. From the dialogue box that opens make your selection of text and bar modifications.

View all MS Project hints and tips


Server loaded in 0.07 secs.