RE: Microsoft Project
Hi Craig
Each resource can have a cost so that when it is assigned to a task Project will calculate the cumulative cost both for the task and for the resource.
There are several ways to assign resources. A very robust and stable way to do this is to split the screen: in the Gantt view, choose window > split. Then click on the task you wish to assign resources to.
Down in the lower left half of the newly split screen you will find you can choose your resources for this task. Finally click on OK to assign them.
I hope this helps - do let us know if we can be of further assistance.