What is the best way of including tasks with mandatory timeframes
RE: project tasks
Hi Muriel
One approach to take is to set a constraint on your task. Double click on the task name and from the advanced tab choose a constraint type that matches how you anticipate this task should be modeled (eg must start on or start no earlier than).
I hope this helps - do let us know if you need any further information.