Split Task

what would be a typical use of "Split Task" ?

RE: Split Task

Hi Andi

Thanks for your question.

Split task is handy to show an activity that starts then for some reason will pause before resuming later on. There is a split task icon on the toolbar. It can also be activated by choosing Edit > Split Task

I hope this helps - do let us know if you have any further questions.

Kind regards,

Andrew

MS Project tip:

Giving Someone a Gantt Chart Snapshot

To pass on a picture of a Gantt chart segment, choose the appropriate view, select the rows to be included, then click on the camera icon and select For Screen. The graphics image can be pasted into another document. (See Paste icon forn Project 2010)