When would you use a finish to finish dependency?

RE: Task Dependencies

Hi Laura

Thank you for your question

A finish to finish dependency means that the successor task cannot finish until the predecessor task has also finished.

For example if you were running a music festival, you wouldn't want the security cover to finish before the end of the last act. So a finish to finish link from the last act to security cover could be set, perhaps with some lag time to allow for crowd dispersal.

Hope this helps

Regards

Stephen

MS Project tip:

Inserting Task Durations Quickly

When entering durations for your tasks simply use the single letters - m for min, h for hr, d for day, w for week, but mon for month. If default is set for days, you need only type the number, for example 3 for 3days, or 0.5 for half a day.