James has attended:
Project Intro Intermediate course
Working times
If i have started a programme and it was based on 5 days working week how can i make some weekends count as the working time
RE: Working times
Hi James
Thanks for your question
The crucial question is are all or only some of your resources going to work on these selected weekends?
If all, then I suggest selecting the weekends in question on the project default calendar and setting them to working time.
If only a specific group of resources will be working then I suggest you create a base calendar for those resources and set the weekends to working.
If only a few individual resources are to work on these days then it would be best to make the cahnges in the individual resource calendars.
Hope this helps
Regards
Stephen