How do I set task constraints?

RE: Tasks

Hi Alka

Thanks for your question

If you select the relevant task in the GANTT chart and then double click on it, the task information dialog will open.

Select the adavnced tab and you can access the task constraints from that point.

Regards

Stephen

MS Project tip:

Compare Work and Duration

Duration is the timescale within which a task is done; Work is the specific time element used. For example, 3 days work in a duration of 2 weeks. To compare, add the Work field into the Entry table by right clicking a column heading to Add Field.