How can I show many different items on the same task (bar)line ?
RE: project
Hi Garry
Thanks for your question.
First create a summary task with indented items below it.
Select the indented items and press shift + F2 to bring up the multiple task properties dialog box. On the general tab click in the box Roll up Gantt Bar to summary so that a tick is in the box. Click ok.
Next double click your summary task and on the general tab put a tick in the hide task bar check box.
Finally click on the minus symbol beside your summary task to fold up the indented tasks leaving only the rolled up bars appearing on one line.
I hope this is helpful - please do let us know if you need further information.