How do I remove a constraint?

RE: Constraints

Hi Sally

Thanks for your question - to reset your constraint type back to the original setting double click on the task and go to the advanced tab. From there set your contstraint type to "As soon as possible" (generally the default setting).

I hope this is helpful - do let us know if you have any further questions.

Kind regards,

Andrew

MS Project tip:

Link tasks using predecessor column - project

a. First, note ID number of the task you want to link to (predecessor). Then, in the predecessor column of the task you want to link to (successor), type the predecessor task's ID number.
b. The link will be a Finish to Start (the default type).
c. Or you can add in a code for a different relationship type
i. SS = Start to Start
ii. FF = Finish to Finish
iii. SF = Start to Finish
d. You don't have to type the task ID numbers in any specific order, but you must separate multiple tasks with commas.

View all MS Project hints and tips