how do you link tasks to resource availability, ie if you have limited availability of resource how do you get the tasks to snap to the availability time
RE: linking tasks to resource availability
Hi Jason,
Thankyou for your question
The best way to accomplish this is to have the Automatic Levelling switched on. This will automatically attempt to resolve resourcing issues as they occure, and one method will be to split and delay tasks in line with resource availability.
I would caution however, that automatic levelling can result in rapid and radical alterations to a project plan and should be used with caution