project server training online - current date

Forum home » Delegate support and help forum » Microsoft Project Training and help » project server training online - Current Date

project server training online - Current Date

resolvedResolved · Low Priority · Version Standard

Richard has attended:
Project Intro Intermediate course

Current Date

Why would I want to change the current date time setting?

RE: Current Date

Hi Richard,

Thanks for your question. One of the reasons you may wish to change the date in Project (Project menu > Project Information) is when you want to update progress (or work complete) on tasks as of a certain date. Project can be set to automatically move any remaining incomplete work to the new current date. This gives you a more accurate picture of how well the project was performing at that date.
Hope this helps - do let us know if you have any further questions.

Kind regards,

Andrew


 

MS Project tip:

Compare Work and Duration

Duration is the timescale within which a task is done; Work is the specific time element used. For example, 3 days work in a duration of 2 weeks. To compare, add the Work field into the Entry table by right clicking a column heading to Add Field.

View all MS Project hints and tips


Server loaded in 0.08 secs.