how do when bring the task numbers onto the main project sheet
RE: task numbers
Hi Ian
The task numbers are stored in a field called ID. To bring this field to appear beside the bars on the chart do the following:
From the Format menu click choose Bar styles...
Choose task style (already chosen by default) and click on the text tab. In the list of slots choose click in the cell besides "left" and from the drop down choose the ID field.
Click OK and now the number will appear beside the tasks.
I hope this is helpful - let us know if you have any further questions.
Kind regards,
Andrew