Forum home » Delegate support and help forum » Microsoft Project Training and help » microsoft project - What are constraints?

microsoft project - What are constraints?

resolvedResolved · Low Priority · Version Standard

Francesca has attended:
Project Intro Intermediate course

What are constraints?

In what circumstances can I use a constraint?

RE: What are constraints?

Hi francesca

Thank you for the question

Tasks constraints generally should be used to represent external constraints; for example a supplier cannot provide vital equipment before a certain date, or we cannot access a building vital to a task until a certain date.

They should however be used sparingy, as every task constraint limits project's ability to represent changes to the schedule that result from such things as task delays, resourcing issues etc.

Regards

Stephen


 

MS Project tip:

MS Project 2010 Scroll to Task

Ever feel lost on a large project file? In Gantt view, Task ribbon, Editing, click on the Scroll to Task tool to centre the task bar on your screen.

Shortcut Ctrl+Shift+F5

Same as Go to Selected Task in MS Project 2003.

View all MS Project hints and tips


Server loaded in 0.07 secs.