project/server/2003/training - resources

Forum home » Delegate support and help forum » Microsoft Project Training and help » project/server/2003/training - Resources

project/server/2003/training - Resources

ResolvedVersion Standard

Steve has attended:
Project Intro Intermediate course

Resources

How do I allocate resources from a common pool and
how do I roll-up the resources allocated to several projects?

RE: Resources

Hi Steve,

Simply create a blank project and then populate the resource sheet with the resources in your common pool. Save this, calling it something like "resource pool" etc.

Then with the resource pool open, open the projects that are to use the resource pool and click on tools-resource sharing-share resources.

Then choose the option that allows the project to get its resources from the resource pool and save the changes.

Then if you reopen the resource pool it will give you the opportunity to open a master project that shows all the rpojects using the resource pool.

Regards

Stephen

MS Project tip:

Enter a Date

You can enter today's date (or tomorrow's date) in a date field, by simply typing in the word 'today'or 'tomorrow' and Project will insert the date for you.

View all MS Project hints and tips

Connect with us:

0207 987 3777

Call for assistance

Request Callback

We will call you back

Server loaded in 0.1 secs.