project server courses - microsoft project

Forum home » Delegate support and help forum » Microsoft Project Training and help » project server courses - Microsoft Project

project server courses - Microsoft Project

resolvedResolved · Low Priority · Version Standard

Meryl has attended:
Project Intro Intermediate course

Microsoft Project

How do I allocate resources to tasks.

RE: Microsoft Project

Hi Meryl,

The easiest way to allocate resources to tasks is to split the GANNT chart view, so that you have the GANNT chart in the upper window, and the task information view in the lower window. Do this by opening the GANNT chart and clicking on Window-Split.

Select the task you wish to allocate resources to in the GANNT chart, then select the resources to allocate in the lower view. Be sure to select all the required resources before clicking "OK", or clicking outside of the lower pane, as once the initial resources are allocated, any further resource changes will change either the task duration, or the total work depending on the task's setting.

Regards

Stephen


 

MS Project tip:

Show or hide toolbar ScreenTips

On the Tools menu, go to Customize, and then select Toolbars.
Click the Options tab.
put a tick or remove the tick from the Show ScreenTips on toolbars check box.

View all MS Project hints and tips


Server loaded in 0.08 secs.