ms project 2003 courses - Resources

ResolvedVersion Standard

Hanna has attended:
Project Intro Intermediate course

Resources

How should annual leave be booked into the project plan.

RE: Resources

Hi hanna

Annual leave should be booked into the project plan by using individual resource calendars. Each resource should be allocated their own calendar that marks their personal availability.