Is it possible to measure costs, actual vs planned?
RE: Costs
Hi James
Thanks for your questions. It is possible but before Project can gather the necessary data you need to save a baseline (Tools > Tracking > Save baseline).
In the Gantt Chart view switch to the Costs table (View > Table > Costs) Here you will see costs, baseline and variance information calculated for you.
As you update your project these figures will automatically adjust.
I hope this is helpful - do let us know if we can be of further assistance.