project.training - Fixed duration

ResolvedVersion Standard

Lindsay has attended:
Project Intro Intermediate course

Fixed duration

What is the difference between a fixed duration of a task and the amount of time you can allocate to a task?

RE: fixed duration

none - duration IS the amount of time you allocate to a task, ie 2 hour meeting

MS Project tip:

Formatting Bar Text

To display notes or resource initials on the Gantt chart bars, choose Format, Bar Styles and the Text tab. Select the position you want to show the text i.e. Top or Inside etc, then choose the field name you are looking for from the drop down arrow. Type the first letter of the name to get quickly to the top of the letter range. Click OK.

View all MS Project hints and tips