RE: Linking the projects
unassign the resource and reassign them using the assign reassign butoon in project
Forum home » Delegate support and help forum » Microsoft Project Training and help » ms project training courses - Linking the projects
unassign the resource and reassign them using the assign reassign butoon in project
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question.
Our Microsoft Qualified trainers will then respond within 24 hours (working days).
Frequently Asked Questions
What does 'Resolved' mean?
Any suggestions, questions or comments? Please post in the Improve the forum thread.
In the Entry table, use the Precessors column to type in links. Type the previous task's ID to link. To change the link, add FS (Finish-Start), FF (Finish-Finish), and so on, and + duration to add a Lag, or - duration for a Lead time. Example: for task 5, 4FS+1w ... task 4 preceeds task 5, finish to start, with a week lag between.
Call for assistance
We will call you back